KIOGORO  INTEGRATED SELF-FINANCING RURAL DEVELOPMENT PROJECT

 

KIOGORO DIVISION IN KISII CENTRAL DISTRICT IN THE REPUBLIC OF  KENYA

INCORPORATING LETS AND COMMUNITY BANKING

 

 

(partnership applications invited)

 

and

NGO STICHTING BAKENS VERZET, WIERINGERWERF, NETHERLANDS


"Money is not the key that opens the gates of the market but the bolt that bars them"

 

Gesell, Silvio The Natural Economic Order

Revised English edition, Peter Owen, London 1958, page 228

 

 

“Poverty is created scarcity”

Wahu Kaara, point 8 of the Global Call to Action Against Poverty, 58th annual NGO Conference, United Nations, New York 7th September 2005.


 (Edition 02 : 10th July, 2008)


 

02.00 GEOGRAPHIC INFORMATION. 

 

02.04 LIST OF VILLAGES IN THE PROJECT AREA

 

02.04.03.01 Sublocation 03 Boronyi :  village 1 Amariba

Inhabitants : 270 households, 2700  population.
Water supply required @ 25l per day = 67500 litres/day.

Available water supply : 1 private well (excluded from the project).

There are also:

1 Primary school

1 Secondary school

 

Dig two new wells.

From the two new wells in or around Amariba, pump a total of 70m3 water per day.

The wells will each be fitted with 6 Solar Spring solar pumps
Each of 10 pumps dedicated to a water tank supplying about 270 users.
One pump system for the primary school.
One pump system for the secondary school.

Triple unit reserve hand-pump-systems next to the new wells.

Each new well system equipped with:
The well itself
Photovoltaic panels for overall +/- 1800Wp ( being 24 x 75Wp panels) and supports with multipoint hand-tracking system.
Six solar pumps with accompanying electronics.
Six 15m3 tanks on tank supports placed in six locations in Amariba, of which one in either the primary school grounds or the secondary school grounds.
A triple hand-pump system as backup.
A Hand-pump platform.
Washing place.
Fence or similar around PV panels.
Paths for users.
Sink pits for water drainage.


 

Next village :

 

Village 03.2 Nyaboterere.

 

Return to:

 

02.04 List of villages.

 


 

Next file :

 

03.01 General project background.

 

Back to:

02.03 General information on the Kiogoro project area.

 


 

Complete project index.

 


 