Director,
T.E.(Terry)
Manning,
Schoener 50,
1771 ED
Wieringerwerf,
The Netherlands.
Tel:
0031-227-604128
Homepage:
http://www.flowman.nl
E-mail:
(nameatendofline)@xs4all.nl : bakensverzet
and
"Money is not
the key that opens the gates of the market but the bolt that bars them"
Gesell, Silvio The
Natural Economic Order
Revised English
edition, Peter Owen,
“Poverty is created scarcity”
Wahu Kaara, point 8 of the Global Call to Action Against Poverty, 58th
annual NGO Conference, United Nations,
02.04 LIST OF VILLAGES IN THE PROJECT AREA
02.04.04.02 Sublocation 04 Masongo : village 2 Otamba
Inhabitants
: 87 households, 874 population.
Water supply required @ 25l per day = 21850 litres/day.
Available
water supply : none.
There are
also:
2 Primary schools
2 Secondary schools
Dig one new well/ or borehole with an internal
diameter of at least
From the
new well in or around Otamba, pump a total of 25m3 water per day.
The well/borehole will be fitted with 8 Solar
Spring solar pumps
Each of 4 pumps dedicated to a water tank supplying about 218 users.
One pump system for each of the two primary schools.
One pump system for each of the two secondary schools.
Triple unit reserve hand-pump-system next to
the new well.
The new
well system equipped with:
The well itself
Photovoltaic panels for overall +/- 2400Wp ( being 32 x 75Wp panels) and
supports with multipoint hand-tracking system.
Eight solar pumps with accompanying electronics.
Eight 15m3 tanks on tank supports placed in eight locations in Otamba, of which
one in each of the primary school
grounds an done in each of the two secondary school grounds.
A triple hand-pump system as backup.
A Hand-pump platform.
Washing place.
Fence or similar around PV panels.
Paths for users.
Sink pits for water drainage.