SANARPATTY INTEGRATED SELF-FINANCING RURAL DEVELOPMENT PROJECT

NEW HORIZONS FOR SANARPATTY

DINDIGUL DISTRICT, TAMIL NADU STATE, INDIA


Edition 01: 23 June, 2003


EXECUTIVE SUMMARY


01. INTRODUCTION

The accompanying Integrated Self-financing Development Project for the Sanarpatty Block in the Dindigul district in Tamil Nadu State in India covers a complete package of basic services for sustainable development in the beneficiary communities. It includes hygiene education, the provision of drinking water and sanitation services, PV lighting for study, waste removal, high-efficiency stoves and bio-mass to fuel them. It provides a strong thrust for on-going local development, productivity, and employment. It contains many decentralised solar energy applications.

The project is strongly demand response oriented. It has been worked out together with the people concerned, who will execute, run, own and pay for it.

The project provides practical working solutions for sustainable integrated development in the Sanarpatty area and covers all major development priorities. It constitutes a practical way of applying modern development concepts such as those outlined in the DFID "Guidance manual on water supply and sanitation programmes" (WEDC for DFID, 1998). It integrates in a practical and feasible manner policy, finance, technology and human capacity building to offer sustainable solutions to development.

The project application are self-financing, subject to an interest-free seed loan repayable in 10years. It is structured for about 12000 extended households (61000 users). The amount of the loan is Euro 3.750.000 or approximately Euro 60 per user. This is repaid by a monthly payment of Euro 0,60 per user into a Cooperative Development Fund. This is enough to cover the basic package offered.

The project requires 75% financing by an External Support Agency within the framework of a country programme with a partner donor. The state of Tamil Nadu is expected to supply the remaining 25%.

The project is self-financing because it allows the recipient communities to fully exploit a network of sustainable development activities using:
(i) The interest-free loan itself
(ii) Local Exchange Trading System (LETS)
(iii) Multiple re-cycled interest-free micro-credits to be administered by a local bank. They are generated by recycling loan repayments and reserves during the loan term.

02. THE MAIN PROJECT PACKAGE

The project is centred on the following main components
i. Hygiene education at community level (Health Clubs) and in schools
ii. Distributed clean drinking water (solar pumps with hand-pumps backup, where possible locally manufactured)
iii. Sustainable sanitation (based on the separation of urine, faeces, grey water, other organic waste)
iv. Supply of efficient stoves for cooking (plus solar cookers)
v. Production of biomass to fuel the cookers
vi. Recycling of non-organic waste products (rubbish collection)
vii. PV lighting for study
viii. Rainwater harvesting
ix. A local PV powered radio station

03. GENERAL ECONOMIC BASES AND PRINCIPLES OF THE PROJECT

a)The project will be financed by interest-free seed capital in the form of a loan repayable over a period of 10 years.

b)75% of this capital will be contributed by an external support agency and the remaining 25% by the Tamil Nadu State Government.

c)General financial supervision will be on terms agreed with the lenders of the seed capital, but with the elimination of unnecessary bureaucratic restraints.

d)Seed capital repaid by users in monthly instalments will be retained in the local area until the end of the loan term. During that time, the repayments will be used to grant revolving interest-free micro-credits for local development.

e)Seed capital not required for short term use, will similarly be used to grant interest-free revolving micro-credits.

f)The local currency (LETS) systems will form the general method of payment for (most) local goods and services at community level, including those provided for the project from within the local community.

g)The part of the maintenance money destined for long term replacement of capital items will also be recycled as interest-free micro-credits until it is needed.

h)Users will be 100% responsible for on-going administration, capital repayments, and maintenance costs. Each household will pay a monthly contribution sufficient to cover those costs. The instalments will be to a large extent covered by savings on funds traditionally spent on fuel, water and waste removal and if possible through the sale of carbon emission reduction certificates under the Kyoto treaty.

i)The project encourages open competition and free enterprise within the framework of a cooperative and non-profit-making global financial structure.

j)Administration, construction and maintenance work will be done by local operators and villagers who will be paid at current local pay rates mostly expressed in the local LETS currency when it is set up.

k)The on-going administration costs of the Project Coordinator are set out in the project budget.

l)Users must make their first monthly contribution in advance, when their project systems are put into use.

m)The tank sangams will be paid a small monthly allowance in formal currency for their work. The well sangams will be paid a monthly allowance under the local LETS currency for their work.

n)Individual women or women's groups will, without payment, each look after their own sanitation units.

o)Regular inspection by installations will be paid as necessary in the local LETS currency.

p)The operation of the local bank will be supported by a leading Green Bank.

q)The Dindigul District Council and the state government of Tamil Nadu will undertake not to intervene to impede the development of the local LETS currency either during or after the project period.

r)The Project Coordinator will reach a specific agreement with the applicable tax authorities before the start of the project as to taxation of activities under the Local Exchange Trading (LETS) system.

s)Before the project starts, a formal agreement will be made to ensure ownership of the project is vested in the beneficiary communities.

 t)Ownership of existing structures may be transferred to or vested in the tank and well sangams to be set up under the project.

04. LONG TERM GOALS OF THE PROJECT

The long term goals of the project are:

a)To sustain on-going improvement of the general quality of life wellbeing and health of the local people and of Dalits and Dalit women in particular.

b)To free more human resources for local production and development.

c)To reduce water-borne diseases so that medical staff and financial resources can be re-directed to other health objectives such as vaccination programmes and preventive medicine.

d)To decrease infant mortality and promote family planning.

e)To increase literacy levels.

f)To eliminate dependency on fuels imported from outside the project area.

g)To help reduce deforestation and global warming.

h)To create value added from locally recycled non-organic solid waste.

i)To create a "maintenance culture" to conserve the investments made.

j)To increase the local pool of expertise so that local people can improve their sustainable well-being and development by identifying and solving problems, including erosion, with a minimum of outside help.

k)To create full employment in the project area.

l)To offer meaningful opportunities to youth and help stop movement of population from rural areas to towns.

05. INSTITUTIONAL STRUCTURES

The various parties which would be presumably usually be involved in project applications are:

i. The Local NGO (DBGDS - District Boodhan Gramadhan Development Sangh)

ii. Project Coordinator, who is from the project area

iii. Consultant to the Project Coordinator

iv. The Organisational Workshops

v. Country programme administrators

vii. Local Funding Authority

viii. Locally Elected MP

ix. Dindigul District council

x. State (Tamil Nadu) Health Authorities

xi. State (Tamil Nadu) Education Department

xii. The Local Tax Authorities

xiii. The Sanarpatty Cooperative Local Development Bank (to be instituted)

xiv. The Central Bank of India - Kambiliampatty and its correspondent in the donor partner's country.

xv. The Local gypsum composites Production Units

xvi. Tank Sangams - the Key Structures

xvii. Well Sangams

xviii. Zimbabwe AHEAD (NGO)

xix. EOS CONSULT

xx. Medical Commissions

xxi. Teachers' Commissions

xxii. The independent auditor

The details of the roles of each of the above and how they all interact with one another are set out in detail in section 2.6 of the project and in the diagrams and charts part of the project documents.

06. SHORT INDICATIVE BUDGET

Item

Outgo (Capital)

Phase

Estimate (Euro)

01

OW health clubs

2

30.000

02

Formation of health clubs

2

10.000

03

Material for health clubs

2

5.000

04

Training of health workers

2

10.000

05

OW health courses in schools

2

10.000

06

Material for school courses

2

2.500

07

OW social structures

2

40.000

08

OW LETS systems

2

60.000

09

Office and equipment LETS systems

2

30.000

10

OW Micro-credit system

2

20.000

11

Office/equipment Micro-credit system

2

10.000

12

OW gypsum composites production units

2

30.000

13

Shovel/preparation anhydrite supply site

2/3

10.000

14

Construction and equipping anhydrite factory (*20000 FOR EACH FACTORY) ASSUMING 3 UNITS

2/3

60.000

15

Moulds for anhydrite products (*20000 FOR EACH FACTORY) ASSUMING 3 UNITS

2/3

60.000

16

Location gypsum depots and quality control

2

3.000

17

OW recycling system

2

30.000

18

Setting up recycling centre network

3

150.000

19

Setting up compost collection network

3

5.000

20

OW Bio-mass system

3

15.000

21

OW Drinking water system

2/3

25.000

22

Setting up of project workplace

2

32.000

23

Project transport

2

100.000

24

Vehicles and materials for wells

3

150.000

25

Fuel and maintenance vehicles

3

26.000

26

Drilling/lining costs

3

200.000

27

Labour for wells - LETS systems

3

pro-memorium

28

63 Washing places- LETS systems

3

pro-memorium

29

63 Platforms for hand-pumps - LETS systems

3

pro-memorium

30

267 Solar Pumps

3

357.000

31

267 Supports for solar panels

3

75.000

32

Solar panels (79.5 kW)

3

496.800

33

Hand-pumps groups (132 pumps)

3

80.000

34

Cables, feed-pipe for pumps/wells

3

98.000

35

Pipe lines from wells to tanks - 150000m @ Euro 0.65

3

100.000

36

Labour for laying water pipelines- LETS

3

pro-memorium

37

267 Water tanks (@ 2m * 1.7m)- mostly LETS

3

60.000

38

267 Bases for water tanks - mostly LETS

3

30.000

39

Supervision of installation and training maintenance operators

3

15.000

40

Purchase spare parts supplies

3

20.000

41

Permits and formalities

2

1.000

42

Preparation and formulation of project specifications

2

6.000

43

100 Solar water purification installations for clinics and schools

3

47.500

44

900 Solar water purification installations (inc.15.000 Wp panels)

4

128.500

45

267 PV lighting units for study purposes

4

200.000

46

PV television for study

4

pro-memorium

47

10 PV lighting systems for schools in villages without electricity

4

10.000

48

PV lighting for clinics outside the project area

4

pro-memorium

49

PV lighting for clinics inside the project area

4

pro-memorium

50

PV refrigeration for clinics @ Euro 5000/clinic

4

pro-memorium

51

Water testing equipment

4

5.000

52

Transport costs Euro to India

2/3

30.000

53

Transport costs internal to Sanarpatty

2/3

22.500

54

Administration and supervision at Sanarpatty India

3/4

36.000

55

Fee Project coordinator and assistant @Euro 50000/year

1/5

100.000

56

General project consulting Manning @Euro 50000/year

1/5

100.000

57

Fund for PV lighting solar home systems

4

180.000

58

Sanitation facilities with exception of some additives will be manufactured and installed within the local LETS systems

3/4

15.000

59

OW radio station

4

25.000

60

Fund for radio station

4

52.000

60

Reserves 8.97% of total

5

336.200

61

General total

5

3.750.000

07. SHORT ANALYSIS

Outgo (Capital)

Phase

Estimate (Euro)

Total first phase

1

0

Total second phase

2

534.500

Total phase 3

3

2.053.300

Total phase 4

4

626.000

Fees project coordinator

1/5

100.000

Total supervision Manning

1/5

100.000

General total all phases

 

3.413.800

Reserves 8.97%

5

336.200

Total 1+2+3+4+5

 

3.750.000

08. ON-GOING COSTS

On-going costs

Euro

 

 

Coordinator for administration

15.000

Maintenance operators

5.000

Tank Sangams (267*5 Euro p.m.)

16.020

Spare parts

15.000

Reserve for theft

15.000

Unforeseen (about 12%)

 8.980

Total recurrent costs

75.000

09. INCOME

Income

Euro

 

 

Annual contribution for use of water (61500 people @ Euro 0.60 p.m.)

442.800

On-gong costs per year

75.000

Net annual income for loan repayment

367.800

10. COMMENTS ON BUDGET

1. The above net income is sufficient to finance and repay an interest free loan for Euro 3.750.000 over a period of 10 years, taking the various reserves into account.
2. Interest-free loan for Gypsum Composites each factory Euro 40.000, for repayment over a period of 3-5 years is included in the above figures.
3. At the end of the ten years' period, on repayment of loan, large capital reserves will be built up for use in Micro-credits and, subsequently, for the extension and renewal of the capital goods.
4. Payments for water facilities for schools and clinics are included in the users' monthly contributions.
5. Payments for PV lighting installations for study purposes will be financed by each tank Sangam area separately.
6. Savings on the purchasing of bio-mass for cooking and the costs of drinking water will at least partly offset the costs of the project.

11. GRAPHS FORMING AN INTEGRAL PART OF THE PROJECT DOCUMENT

GRAPH SHOWING DEVELOPMENT OF MICRO-LOANS
CASH FLOW DIAGRAM
THE INTEREST-FREE LOAN CYCLE
HOW THE ORIGINAL SEED LOAN MONEY IS USED
TYPICAL PROJECT EXPENDITURE BY QUARTER - budget items 01-30
TYPICAL PROJECT EXPENDITURE BY QUARTER - budget items 31-60
TOTAL EXPENDITURE BY QUARTER
DETAILED EXPENDITURE FIRST QUARTER
DETAILED EXPENDITURE SECOND QUARTER
DETAILED EXPENDITURE THIRD QUARTER
DETAILED EXPENDITURE FOURTH QUARTER
DETAILED EXPENDITURE FIFTH QUARTER
DETAILED EXPENDITURE SIXTH QUARTER
DETAILED EXPENDITURE SEVENTH QUARTER
DETAILED EXPENDITURE EIGHTH QUARTER
DETAILED EXPENDITURE NINTH QUARTER
DETAILED FINAL EXPENDITURE

12. RECYCLING OF FUNDS FOR MICRO-LOANS

GRAPH SHOWING DEVELOPMENT OF MICRO-LOANS
THE INTEREST-FREE LOAN CYCLE
HOW THE ORIGINAL SEED LOAN MONEY IS USED

The funds recycled are approximately 17.038.235 Euro. They are made up of:

a) Repayments of the interest-free seed loan itself. These are shown as horizontal lines at the bottom of the micro-loans graph. They are constant. During quarters 42-45 the amounts left for repayment UNDER THE PROJECT are reduced to zero. However users continue to make monthly contributions on their own account, so the recycling of funds will in practice continue. The capital fund will build up again as shown in the micro-loans graph. It will drop again when replacements of the original capital goods are made or the system services extended. It will then build up for a third time to cover further collective capital investments and so on for so long as the users continue making their monthly contributions.

b) Certain capital sums (e.g. repayments for the gypsum composites factories) and reserves.

c) Repayments under the micro-loans. These are seen as diagonal lines in the micro-loans graph. Towards the end of the project period, payback times are shortened to ensure capital re-enters in time for repayment of the original seed loan.


13. ACCESS TO THE COMPLETE PROJECT

The project has been placed in the pubic domain and can be freely accessed and downloaded together with drawings, charts and graphs in colour together from the home page of the website : www.flowman.nl

14. LIST OF KEY WORDS

Anhydrite use of, Banks role of in development, gypsum composites, Bio-mass for cooking, Briquettes bio-mass, Capacitation workshops, Chain control integral, Clodomir Santos de Morais, CO2 emissions reduction of, Communication flows in development projects, Compost recycling, Composting toilets, Cookers high efficiency, Cooperation role in development, Development projects structures for, Development sustainable, Drinking water supply, Economy developing countries, Economy development projects, Economy foreign aid, Economy industrial development, Economy interest-free development, Economy Local Exchange Trading (LETS) systems, Economy nominal local currencies development of, Economy micro credits, Economy self-financed development, Economy taxation and development, Education hygiene, Gender role of women, Gypsum cheap, Hand pumps, Health Clubs development projects, Hygiene education, India integrated development, Industrial development, Information flow in development projects, Integral chain control, Integrated development projects, Interest role of, LETS systems, Loans interest-free, Local currency systems, Local Exchange Trading (LETS) systems, Micro-credit systems, Morais Clodomir Santos de, Organizational workshops (OW), Sanarpatty India development, Photovoltaic (PV) home systems, Photovoltaic (PV)lighting, Photovoltaic (PV) pumps, Photovoltaic (PV) refrigeration, Poverty alleviation, Products regeneration of, Pumps solar, Pumps hand, Rainwater harvesting, Recycling compost, Recycling shops, Recycling waste, Regeneration of products, Rural water supply, Sanitation developing countries, Sanitation dry, Self-financing development projets, solar pumps submersible, Stoves high efficiency, Sustainable development, Tamil Nadu Sanarpatty development, Tanks gypsum composites local manufacture, Toilet facilities gypsum composites, Toilets dry, Urine disposal, Washing places, Waste collection systems, Water purification UV, Water supply projects, Water supply rural, Water tanks gypsum composites, Women role of in development, Workshops Moraisian

 


RETURN TO:

 

MAIN PROJECT DOCUMENT

 


List of attachments.

List of draft projects in English and French.

Main project programme.

Model Homepage.

Homepage Bakens Verzet