Fourth block: The structures to be created.

 

Value : 03 points out of 18

Expected work load: 96 hours out of 504

 

The points are finally awarded only on passing the consolidated exam for Section B : Solutions to the Problems.

 


 

Fourth block: The structures to be created.

 

Section 1. Justification of the order of sequence for the creation of the structures. [16 hours]

 

14.00 hours:  Justification of the order of sequence for the creation of the structures.

02.00 hours : Preparation report.

 


 

Section 1. Justification of the order of sequence for the creation of the structures. [16 hours]

 

14.00 hours:  Justification of the order of sequence for the creation of the structures.

 

1. Nesting and subsidiarity.

2. Moraisian workshops.

3. The first phase of execution.

4. The second phase of execution.

5. The third phase of execution.

6. Chart showing the execution structures.

7. Activity plan.

 


 

02.00 hours : Preparation report.

 


 

14.00 hours:  Justification of the order of sequence for the creation of the structures.

 

7. Activity plan. (At least two hours)

 

Click here to see a typical activities plan for the execution of an individual integrated development project. The description of each item contains an indication of the parties involved in the activity in question.

 

The plan enables standard project progress to be traced month by month .

 

Items 60101-61901 cover the main structures to be established during project execution. The 19 structures involved are numbered 601-619.

 

1. Research.

 

On two pages note the expected time for the commencement of each activity and explain the reasons for the specific order of sequence for their execution.

 

To see a graphic summary of the activities for each quarter, see :

 

Quarterly activities. 

 

2. Research.

 

Make a list of the quarters. Next to each quarter make a second column, with a list of the five main activities from the point of view of the investment  needed. Next to each group of five activities make a third column and write in the budget  amount for each of the five activities. Next to the budget  amount make a fourth column with your comments. Bear in mind that most activities take place over several quarters.

 

Here is a typical plan for the purchase of services and goods for individual integrated development projects.

 

4.Procurement calendar.

 

4.1 Procurement calendar listed by budget item.

 

2A.SERVICES.

 

1.        Budget item 1010101: Project coordinator. Month 1.Duration 1 week.

2.        Budget item 70301: Consultant assistant to project coordinator. Month 1. Duration 1 week.

3.        Budget item 70302: Hygiene education consultant. Month 1. Duration 1 week.

4.        Budget item 70303: Consultant for Moraisian workshops. Month 1. Duration 1 week.

5.        Budget item 70306: Gypsum composites consultant. Month  3. Duration 1 week.

6.        Budget item 70304: Transport Europa-(host country). Month 3. Duration 1 month.

7.        Budget item 70305: Local transport. Month 3. Duration 1 month.

 

2B.SUPPLIES.

 

01.Budget item 70202 :Means of transport for recycling-sanitation network. Month 4. Duration 2 months.
02.Budget item 70203 :Solar pumps with controllers. Month 10. Duration 2 months.
03.Budget item 70204 :Solar photovoltaic panels (189*300 W = 56.7 kW). Month 10. Duration 2 months.
04.Budget item 70205 :96 hand pumps (including (number) triple groups) entirely from stainless steel. Month 4. Duration 2 months.
05.Budget item 70206 :Cables, feed-pipes, accessories for pour pumps/wells. Month 4. Duration 2 months.
06.Budget item 70207 :Feed-pipes to water tanks – 200000m @ Euro 0.75. Month 10. Duration 2 months.
07.Budget item 70209 :Water purification installations in clinics and schools (back-up) Month 12. Duration 3 months.
08.Budget item 70210 :189 photovoltaic lighting systems for study purposes. Month 3. Duration 3 months.
09.Budget item 70211: Photovoltaic lighting for schools. Month 6. Duration 3 months.
10.Budget item 70212: Photovoltaic lighting/installation for clinics. Month 7. Duration 2 months.
11.Budget item 70213: Photovoltaic refrigeration/installation in clinics Month 10. Duration 2 months.
12.Budget item 70216: Offices and furniture 32 local money transaction registration systems. .Month 2. Duration 2 months.
13.Budget item 70217: Main computer local money transaction registration systems and back-up. Month 2. Duration 2 months.
14.Budget item 70218: 60 computers for local money transaction registration systems.  Month 2. Duration 2 months.
15.Budget item 70219: 64 photovoltaic power systems and accessories local money transaction registration systems. Month 2. Duration 2 months.
16.Budget item 70220: Water quality testing equipment. Month 10. Duration 2 months.
17.Budget item 70221: Equipment (including presses) for the production of mini-briquettes Month 10. Duration 2 months.

 

2C.WORKS.

 

1.Budget item 70101: Construction of 32  8” interior diameter boreholes. Month 3. Duration 2 months.

 

4.2 Procurement calendar : by sequence (month) of execution.

 

Month 1 :

 

Services.

 

1.Budget item 1010101: Project coordinator. Month 1.Duration 1 week.

2. Budget item 70301: Consultant assistant to project coordinator. Month 1. Duration 1 week.

3. Budget item 70302: Hygiene education consultant. Month 1. Duration 1 week.

4. Budget item 70303: Consultant for Moraisian workshops. Month 1. Duration 1 week.

 

Month 2:

 

Supplies:

 

13.Budget item 70217: Main computer local money transaction registration systems and back-up. Month 2. Duration 2 months.
14.Budget item 70218: 60 computers for local money transaction registration systems.  Month 2. Duration 2 months.
15.Budget item 70219: 64 photovoltaic power systems and accessories local money transaction registration systems. Month 2. Duration 2 months.

 

Month 3:

 

Services.

 

5. Budget item 70306: Gypsum composites consultant. Month  3. Duration 1 week.

6. Budget item 70304: Transport Europa-(host country). Month 3. Duration 1 month.

7. Budget item 70305: Local transport. Month 3. Duration 1 month.

 

Supplies:

 

08.Budget item 70210 :189 photovoltaic lighting systems for study purposes. Month 3. Duration 3 months.

 

Works:

 

1.Budget item 70101: Construction of 32  8” interior diameter boreholes. Month 3. Duration 2 months.

 

Month 4:

 

Supplies:

 

01.Budget item 70202 :Means of transport for recycling-sanitation network. Month 4. Duration 2 months.
05.Budget item 70206 :Cables, feed-pipes, accessories for pour pumps/wells. Month 4. Duration 2 months.

 

Month 6:

 

Supplies:

 

09.Budget item 70211: Photovoltaic lighting for schools. Month 6. Duration 3 months.

 

Month 7:

 

Supplies:

 

10.Budget item 70212: Photovoltaic lighting/installation for clinics. Month 7. Duration 2 months.

 

Month 10:

 

Supplies:

 

02.Budget item 70203 :Solar pumps with controllers. Month 10. Duration 2 months.
03.Budget item 70204 :Solar photovoltaic panels (189*300 W = 56.7 kW). Month 10. Duration 2 months.
06.Budget item 70207 :Feed-pipes to water tanks – 200000m @ Euro 0.75. Month 10. Duration 2 months.
11.Budget item 70213: Photovoltaic refrigeration/installation in clinics Month 10. Duration 2 months.
16.Budget item 70220: Water quality testing equipment. Month 10. Duration 2 months.
17.Budget item 70221: Equipment (including presses) for the production of mini-briquettes Month 10. Duration 2 months.

 

Month 12:

 

Supplies:

 

07.Budget item 70209 :Water purification installations in clinics and schools (back-up) Month 12. Duration 3 months.

The activities in the procurement plan usually precede those for  execution of the project structures. Read the 17 items in list 2B above and the periods between procurement and the execution of the structures.

 

3. Opinion.

 

Taking the reality in your chosen area into account, give a one page indication on whether you think the procurement periods are adequate. If you think they should be changed, give an alternative time for delivery explain why you think it is necessary.

 

Once you have completed your work on this section you can proceed with the  preparation of your report on the justification of the order of sequence for the creation of the structures.

 



 Fourth block :  Section 1. Justification of the order of sequence for the creation of the structures.

 Fourth  block : The structures to be created.


Main index  for the Diploma in Integrated  Development  (Dip. Int. Dev.)

 List of key words.

 List of references.

  Course chart.

 Technical aspects.


 Courses available.

Homepage Bakens Verzet


 

Creative Commons License

 

This work is licensed under a Creative Commons Attribution-Non-commercial-Share Alike 3.0 Licence.