NGO
Another Way (Stichting Bakens
Verzet), 1018 AM
01. E-course : Diploma in Integrated Development (Dip. Int.Dev.)
Edition
01: 24 January, 2011
Edition
03 : 16 February, 2011
Study points
: 05 points out of 18
Minimum study
time : 125 hours out of 504
The study
points are awarded upon passing the consolidated exam for
Section C : The Model.
[Study points 03 out of
18]
[Minimum study time: 85 hours
out of 504]
The study
points are awarded upon passing the consolidated exam for
Section C : The Model.
Sect. 5 : Kyoto Treaty : Analysis
of possibilities for finance. (Additional)
03. Potential areas of application of CDM
mechanisms to integrated development projects.
04. Small-scale CDM activities.
06. Selection of the CDM
methodologies for the applications listed in section 03.
08. Notes specific to the role of bamboo in afforestation and reforestation (AR)
projects.
09. CDM funding indications for
the selected applications and methodologies.
09. CDM funding indications for
the selected applications and methodologies.
The chosen methodology AMS-I-A has already been approved for
applications relating to both wind and solar energy and to biomass applications
for electricity generation including but not limited to palm oil and manures
using stand-alone mini-grids with installed capacity less than 15MW or individual structures each with emissions
reductions less than 5 tonnes of CO2e per year.
As a type I small-scale
methodology, methodology AMS-I-A applies
where the total installed capacity is less than 15 MW (or equivalent).
Replacement of kerosene
lamps by LED lamps has been covered under application 09-11. Replacement of kerosene lamps, incandescent
light bulbs, and of the use of throw-away batteries by renewable energy sources
(wind, solar and/or renewable bio-mass including but not limited to plant oil,
gasification of biomass).
This application can be
selectively used for the following, and other, purposes, according to the
requirements of each project area :
a)
b) A mini-grid or equivalent
to support existing non-renewable lighting for local commercial activities.
c) A mini-grid or equivalent
to support existing cooling facilities for local commercial activities.
d) Renewable energy
operation of existing non-renewable diesel-driven equipment such as water pumps
and mills.
It is not clear how
solar-powered battery chargers for rechargeable radio and torch batteries could
be included in this application as the CDM system
applies only to CO2 savings, and not to non-rechargeable batteries and the
environmental aspects relating to their loss in the environment.
The text of the methodology
reads:
“This category comprises renewable electricity generation units that supply
individual households/users or groups of households/users included in the
project boundary. The applicability is limited to individual households and
users that do not have a grid connection except when;
<“(a) A group of households or users are supplied electricity through a standalone mini-grid powered by renewable energy generation unit(s) where the capacity of the generating units does not exceed 15 MW (i.e., the sum of installed capacities of all renewable energy generators connected to the mini-grid is less than 15 MW) e.g., a community based stand-alone off-the-grid renewable electricity systems; or>“(b) The emissions reduction
per renewable energy based lighting system is less than 5 tonnes of CO2e a year and where it can be shown that fossil fuel
would have been used in the absence of the project activity by;
(i) A representative sample survey (90%
confidence interval, ±10% error margin) of target households; or
(ii) Official statistics from the host country government agencies.”
Integrated development projects in urban areas are likely to have a
greater use for this application than rural ones, which are usually so poorly
served that there are few existing structures using non-renewable energy. It is
assumed here that project areas are poorly equipped with commercial and
industrial equipment. The following hypothetical examples are therefore
conservative.
Integrated development project areas contain about 45 intermediate level
administrative units each serving about 1.500 people, and about 250 local
administrative units each typically serving about 250 people.
Taking each of the listed categories
in turn :
a) Street lighting. Suppose
each local administrative unit has, on an average, 2 street lights and that
each light burns
Two installations each with an average installed capacity
of 100W (or thermal equivalent) for each lighting system for each local
administrative unit are assumed. That would produce 500
systems x 100 W installed, being 50000 W, or 50 KW installed capacity..
b) Lighting appliances for
commercial activities. Suppose each local administrative unit has, on an
average, five families out of 50 each using 2 lights for commercial purposes
and that each light burns
There are about 250 local
administrative units in each integrated development project area. Each
integrated development project area would therefore use 250 x
Assuming 5 families each with two lamps, each lamp with
an average installed capacity of 100W (or thermal equivalent) in each of 250
local administrative units, total installed capacity
would be 1 KW for each local development area. 1 KW installed in each of 250
local development areas gives a total installed capacity of 250 KW.
c) Cooling appliances for
commercial activities. Suppose each intermediate administrative unit has, on an
average, one commercial activity using a refrigerator-cooler-freezer with a
consumption of 0.25 kw/hour or 6 kWh/day. There are
about 45 intermediate administrative units in each integrated development
project area. Each integrated development project area would therefore use 6 x
45 kWh or 270 kWh per day. 270 kWh per
day x 365 = 98.550 kWh per year.
1 terajoule
= about 277.778 kWh.
So 98.550 kWh = about 0.35 TJ.
The default factor
for diesel is about 74 tonnes of CO2 per terajoule.
Diesel equivalent
consumed by refrigerators/freezers is 74 x 0.35 = about 26 tonnes of CO2.
26 tonnes of CO2 @
about € 14 (14th November 2009) = € 364 per year.
Assuming installation of and installed
capacity of 2
KW (or equivalent) for each of the 45 intermediate development units, 2 KW by
45 gives a total installed capacity of 90 KW.
d) Replacement of
diesel-driven milling and pumping equipment.
Suppose each intermediate
administrative unit has, on an average, one commercial activity using a diesel-driven
motor with a rated power of 10 hp (about 7.5 kW) operating over 10 hours per
day. 10 hours at 7.5 kW = 75 kWh.
There are about 45
intermediate administrative units in each integrated development project area.
Each integrated development project area would therefore use 45 x 75 kWh or 3.375 kWh per day. 3.375 kWh per day x
365 = 1.231.875 kWh per year.
1 terajoule
= about 277.778 kWh.
So 1.231.875 kWh = about 4.43 TJ.
The default factor
for diesel is about 74 tonnes of CO2 per terajoule.
Diesel equivalent
consumed by refrigerators/freezers is 74 x 4.43 = about 327.82 tonnes of CO2.
327.82 tonnes of
CO2 @ about € 14 (14th November 2009) = about € 4.590 per year.
Assuming the presence of just
one commercial activity in each of the 45 intermediate development unit areas,
and installed capacity of 15 KW (or equivalent), the total installed capacity
would be 45 x 15 KW for a total of 675 KW.
The total installed capacity
under points a) + b) + c) + d) amounts
to just 1.065 KW, or 1,065 MW (or equivalent) part of the 15 MW (or equivalent)
foreseen for applications under methodology AMS-I-A.
Large margins therefore exist
to extend the reach application 12 where local circumstances permit.
The typical accumulative CO2
savings in each integrated development project area under application 12 might
therefore be to the order of € 24.000 per year (totals a) +b)+c)+d)) , or €
506.557 over 21 years. This amount is, however, subject to the
deduction of DOE (designated operational entity ) verification costs. It is
assumed these can be reduced to a nominal figure within the framework of a
widely applicable general convention of the type foreseen.
Although the total is low and the expected verification costs relatively high, the amount can still cover up to 10% of the formal money costs of an integrated development project.
CO2 savings would be higher
where projects are carried out in poor urban areas.
Supposing 2.500 applications
under a sub-regional project, the amount in question is 2.500 x 506.557,
or € 1.266.392.500.
Menu for : 09. CDM funding indications for
the selected applications and methodologies.
09-08. Use of renewable
biomass instead of non-renewable biomass with improved cook stoves.
09-09. Recycling of human
waste to avoid the use of industrial fertilisers.
Exam Block 8 : [4 hours]
Consolidated exam :
Section C. [6 hours].
◄ Eighth block : Section. 5 : Kyoto Treaty : Analysis
of possibilities for finance.
◄ Eighth block : Economic Aspects.
◄ Main index for the Diploma in Integrated Development
(Dip. Int. Dev.)
"Money is not the key that opens the gates of the market but the
bolt that bars them."
Gesell, Silvio, The Natural Economic Order,
revised English edition, Peter Owen,
“Poverty is created scarcity”
Wahu Kaara,
point 8 of the Global Call to Action Against Poverty, 58th annual
NGO Conference, United Nations,
This
work is licensed under a Creative Commons
Attribution-Non-commercial-Share Alike 3.0 Licence.